- Late Nov. 2018: Refinement of LPA
- Dec. 2018: Project Kickoff Meeting
- Late Dec. 2018: Develop STOPS Ridership
- Feb. 2019: Scoping Meeting
- Nov. 2018 - Oct. 2019: Development of DEIS
- Oct. - Nov. 2019: Review of DEIS
- Nov. 2018 - Jan. 2020: Develop Conceptual Engineering Plans
- Nov. 2019 - Jan. 2020: Develop O&M Costs
- Nov. 2019 - Jan. 2020: Develop Capital Costs
- Dec. 2019 - Jan. 2020: Develop Local Revenue Evaluation
- Jan. 2020: Publish DEIS
- Jan. 2020 - Feb. 2020: Preliminary Project Evaluation
- Mar. 2020 - Jun. 2020: Prepare FEIS and Conceptual Design Package
- Summer 2020: Publish FEIS
- Summer 2020: Publish Findings Statement
About
Schedule
The Environmental Impact Statement is expected be completed with a Findings Statement by late 2020. The timeline for the project is estimated as follows:
2020-2022
- FTA Project Development
2022-2025
- Final Design & Engineering
2026-2030
- Construction
2030
- Service begins